Skip to content

Program Management

Mark Linkmeyer edited this page Jul 18, 2017 · 146 revisions

To see larger versions of the images below, right-click on them and open them in a separate browser tab or window.

Development Workflow, Issue Types, and Status Definitions

For information on these see the Jira Usage Help page located here: https://wiki.zephyrproject.org/view/Jira_Usage_Help.

Execution Monitoring

See the Execution Dashboard for the current release (which is in development) here: Current Release Execution Dashboard

See the Bug Lists for the current release (which is in development) here: Current Release Bug Lists Dashboard

Zephyr Project Feature Road Map

Feature Road Map

Schedule

Schedule Milestones

The following graphic shows the timeline of phases and milestones associated with each release:

Schedule Milestones Graphic

This shows how the phases and milestones of one release overlap with those of the next release:

Overlapping Release Schedules Graphic

Milestone Definitions

Milestone Also Called Definition
P0 Planning Kickoff
  • Reminder Email Sent to Kickoff Planning
  • Start Entering Epics, Stories, Tasks
P1
  • TSC Agrees on Major Features / Epics and Schedule
M0 Merge Window Open
  • All Stories & Tasks Prioritized, Sized, and Assigned
  • All Stories Are Associated with Appropriate Epics
  • All Major Feature Stories Are Labeled Accordingly
  • Merge Window Is Opened
M1 M1 Checkpoint
  • Checkpoint for P1s and P2s
M2 M2 Checkpoint
  • Major Features Ready for Code Reviews
  • Test Plans Reviewed and Approved
M3 Feature Merge Window Close
  • Feature Freeze
  • Feature Development Complete (including Code Reviews and Unit Tests Passing)
  • P1 Stories Implemented
  • Feature Merge Window Is Closed
  • Test Development Complete
  • Technical Documentation Created/Updated and Ready for Review
  • CCB Control Starts
M4 Code Freeze
  • Code Freeze
  • RC3 Tagged and Built
M5 Release
  • TSC Reviews the Release Criteria Report and Approves Release
  • Final RC Tagged
  • Make the Release

Planned, Trend, and Actual Dates

Notation: wXX.Y - where X is the week number of the year (with weeks starting on Mon) and Y is the day of the week (1=Mon, 2=Tue, ... 6=Sat, 7=Sun)

1.9 Schedule

Milestone Original Plan Re-Planned Trend Actual Notes
P0 22-Mar-17 (w12.3) 31-Mar-17 (w13.5)
P1 12-Apr-17 (w15.3) 01-Jun-17 (22.4)
M0 31-May-17 (w22.3) 15-Jun-17 (w24.4)
M1 21-Jun-17 (w25.3) 05-Jul-17 (w27.3) 05-Jul-17 (w27.3)
M2 12-Jul-17 (w28.3) 19-Jul-17 (w29.3) 19-Jul-17 (w29.3) Trending one week later than planned per TSC's guidance
M3 02-Aug-17 (w31.3) 09-Aug-17 (w32.3) 09-Aug-17 (w32.3) Trending one week later than planned per TSC's guidance
M4 23-Aug-17 (w34.3) 23-Aug-17 (w34.3) 23-Aug-17 (w34.3)
M5 30-Aug-17 (w35.3) 30-Aug-17 (w35.3) 30-Aug-17 (w35.3)

Planned Milestone Dates for Future Releases

Version P0 P1 M0 M1 M2 M3 M4 M5
1.10 21-Jun-17 (w25.3) 12-Jul-17 (w28.3) 30-Aug-17 (w35.3) 20-Sep-17 (w38.3) 11-Oct-17 (w41.3) 01-Nov-17 (w44.3) 22-Nov-17 (w47.3) 29-Nov-17 (w48.3)
1.11 20-Sep-17 (w38.3) 11-Oct-17 (w41.3) 29-Nov-17 (w48.3) 27-Dec-17 (w51.3) 10-Jan-18 (w02.3) 31-Jan-18 (w05.3) 21-Feb-18 (w08.3) 28-Feb-18 (w09.3)
1.12 27-Dec-17 (w51.3) 10-Jan-18 (w02.3) 28-Feb-18 (w09.3) 21-Mar-18 (w12.3) 11-Apr-18 (w15.3) 02-May-18 (w18.3) 23-May-18 (w21.3) 30-May-18 (w22.3)
1.13 21-Mar-18 (w12.3) 11-Apr-18 (w15.3) 30-May-18 (w22.3) 20-Jun-18 (w25.3) 11-Jul-18 (w28.3) 01-Aug-18 (w31.3) 22-Aug-18 (w34.3) 29-Aug-18 (w35.3)
1.14 20-Jun-18 (w25.3) 11-Jul-18 (w28.3) 29-Aug-18 (w35.3) 19-Sep-18 (w38.3) 10-Oct-18 (w41.3) 31-Oct-18 (w44.3) 21-Nov-18 (w47.3) 28-Nov-18 (w48.3)

Schedule Details

For more details about the project phases, milestones, etc. see More Schedule Details

Clone this wiki locally