Program Management

Kumar Gala edited this page Mar 20, 2019 · 146 revisions

To see larger versions of the images below, right-click on them and open them in a separate browser tab or window.

Schedule

Schedule Milestones

The following graphic shows the timeline of phases and milestones associated with each release:

Schedule Milestones Graphic

This shows how the phases and milestones of one release overlap with those of the next release:

Overlapping Release Schedules Graphic

Milestone Definitions

Milestone Also Called Definition
P0 Planning Kickoff
  • Start Entering Requirements
P1
  • TSC Agrees on Major Features and Schedule
M0 Merge Window Open
  • All features, Sized, and Assigned
  • Merge Window Is Opened
M1 M1 Checkpoint
  • Major Features Ready for Code Reviews
  • Test Plans Reviewed and Approved
M2 Feature Merge Window Close
  • Feature Freeze
  • Feature Development Complete (including Code Reviews and Unit Tests Passing)
  • P1 Stories Implemented
  • Feature Merge Window Is Closed
  • Test Development Complete
  • Technical Documentation Created/Updated and Ready for Review
  • CCB Control Starts
M3 Code Freeze
  • Code Freeze
  • RC3 Tagged and Built
M4 Release
  • TSC Reviews the Release Criteria Report and Approves Release
  • Final RC Tagged
  • Make the Release

Planned Milestone Dates

Version 1.14
P0 27-Jun-18
P1 18-Jul-18
M0 5-Sep-18
M1 26-Sep-18
M2 08-Feb-19
M3 15-March-19
M4 05-April-19 12-April-19

Schedule Details

For more details about the project phases, milestones, etc. see More Schedule Details