Program Management

Mark Linkmeyer edited this page Jun 28, 2017 · 146 revisions

To see larger versions of the images below, right-click on them and open them in a separate browser tab or window.

Execution Monitoring

See the Execution Dashboard for the current release (which is in development) here: Current Release Execution Dashboard

See the Bug Lists for the current release (which is in development) here: Current Release Bug Lists Dashboard

Zephyr Project Feature Road Map

Feature Road Map

Schedule

Schedule Milestones

The following graphic shows the timeline of phases and milestones associated with each release:

Schedule Milestones Graphic

This shows how the phases and milestones of one release overlap with those of the next release:

Overlapping Release Schedules Graphic

Milestone Definitions

Milestone Also Called Definition
P0 Planning Kickoff
  • Reminder Email Sent to Kickoff Planning
  • Start Entering Epics, Stories, Tasks
P1
  • TSC Agrees on Major Features / Epics and Schedule
M0 Merge Window Open
  • All Stories & Tasks Prioritized, Sized, and Assigned
  • All Stories Are Associated with Appropriate Epics
  • All Major Feature Stories Are Labeled Accordingly
  • Merge Window Is Opened
M1 M1 Checkpoint
  • Checkpoint for P1s and P2s
M2 M2 Checkpoint
  • Major Features Ready for Code Reviews
  • Test Plans Reviewed and Approved
M3 Feature Merge Window Close
  • Feature Freeze
  • Feature Development Complete (including Code Reviews and Unit Tests Passing)
  • P1 Stories Implemented
  • Feature Merge Window Is Closed
  • Test Development Complete
  • Technical Documentation Created/Updated and Ready for Review
  • CCB Control Starts
M4 Code Freeze
  • Code Freeze
  • RC3 Tagged and Built
M5 Release
  • TSC Reviews the Release Criteria Report and Approves Release
  • Final RC Tagged
  • Make the Release

Planned, Trend, and Actual Dates

Notation: wXX.Y - where X is the week number of the year (with weeks starting on Mon) and Y is the day of the week (1=Mon, 2=Tue, ... 6=Sat, 7=Sun)

1.9 Schedule

Milestone Planned Trend Actual Notes
P0 22-Mar-17 (w12.3) 31-Mar-17 (w13.5)
P1 12-Apr-17 (w15.3) 01-Jun-17 (22.4)
M0 31-May-17 (w22.3) 15-Jun-17 (w24.4)
M1 21-Jun-17 (w25.3) 21-Jun-17 (w25.3)
M2 12-Jul-17 (w28.3) 12-Jul-17 (w28.3)
M3 02-Aug-17 (w31.3) 02-Aug-17 (w31.3)
M4 23-Aug-17 (w34.3) 23-Aug-17 (w34.3)
M5 30-Aug-17 (w35.3) 30-Aug-17 (w35.3)

Planned Milestone Dates for Future Releases

Version P0 P1 M0 M1 M2 M3 M4 M5
1.10 21-Jun-17 (w25.3) 12-Jul-17 (w28.3) 30-Aug-17 (w35.3) 20-Sep-17 (w38.3) 11-Oct-17 (w41.3) 01-Nov-17 (w44.3) 22-Nov-17 (ww47.3) 29-Nov-17 (w48.3)

Schedule Details

For more details about the project phases, milestones, etc. see More Schedule Details

Issue Types, State Definitions, and Development Workflow

For information on these see the Jira Usage Help page located here: https://wiki.zephyrproject.org/view/Jira_Usage_Help.

Clone this wiki locally