Program Management

Mark Linkmeyer edited this page Jun 14, 2017 · 146 revisions

Zephyr Project Feature Road Map

Feature Road Map

Schedule

Schedule Milestones

The following graphic shows the timeline of milestones associated with each release:

Schedule Milestones Graphic

This graphic shows how the milestones of one release overlap those with the next release:

Overlapping Release Schedules Graphic

Milestone Definitions

Milestone Also Called Definition
P0 Planning Kickoff
  • Reminder Email Sent to Kickoff Planning
  • Start Entering Epics, Stories, Tasks
P1
  • TSC Agrees on Major Features / Epics and Schedule
M0 Merge Window Open
  • All Stories & Tasks Prioritized, Sized, and Assigned
  • All Stories Are Associated with Appropriate Epics
  • All Major Feature Stories Are Labeled Accordingly
  • Merge Window Is Opened
M1 M1 Checkpoint
  • Checkpoint for P1s and P2s
M2 M2 Checkpoint
  • Major Features Ready for Gerrit Reviews
  • Test Plans Reviewed and Approved
M3 Feature Merge Window Close
  • Feature Freeze
  • Feature Development Complete (including Gerrit Reviews and Unit Tests Passing)
  • P1 Stories Implemented
  • Feature Merge Window Is Closed
  • Test Development Complete
  • Technical Documentation Created/Updated and Ready for Review
  • CCB Control Starts
M4 Code Freeze
  • Code Freeze
  • RC3 Tagged and Built
M5 Release
  • TSC Reviews the Release Criteria Report and Approves Release
  • Final RC Tagged
  • Make the Release

Planned, Trend, and Actual Dates

1.9 Schedule

Milestone Planned Trend Actual Notes
P0 22-Mar-17 (w12.3) 31-Mar-17 (w13.5)
P1 12-Apr-17 (w15.3) 01-Jun-17 (22.4)
M0 31-May-17 (w22.3) 15-Jun-17 (w24.4) Trending late due to delayed release of 1.8
M1 21-Jun-17 (w25.3) 21-Jun-17 (w25.3)
M2 12-Jul-17 (w28.3) 12-Jul-17 (w28.3)
M3 02-Aug-17 (w31.3) 02-Aug-17 (w31.3)
M4 23-Aug-17 (w34.3) 23-Aug-17 (w34.3)
M5 30-Aug-17 (w35.3) 20-Aug-17 (w35.3)

Notation: wXX.Y where X is the week number (that starts on Mondays) and Y is the day of the week (1=Mon, 2=Tue, ... 6=Sat, 7=Sun)

Planned Milestone Dates

Content coming...

Schedule Details

Content coming...