The following graphic shows the timeline of phases and milestones associated with each release:
This shows how the phases and milestones of one release overlap with those of the next release:
Milestone | Also Called | Definition |
---|---|---|
P0 | Planning Kickoff |
|
P1 |
|
|
M0 | Merge Window Open |
|
M1 | M1 Checkpoint |
|
M2 | M2 Checkpoint |
|
M3 | Feature Merge Window Close |
|
M4 | Code Freeze |
|
M5 | Release |
|
Version | 1.11 | 1.12 | 1.13 |
---|---|---|---|
P0 | 20/09/2017 | 27-Dec-17 | 21-Mar-18 |
P1 | 11/10/2017 | 10-Jan-18 | 11-Apr-18 |
M0 | 29/11/2017 | 28-Feb-18 | 30-May-18 |
M1 | 27/12/2017 | 21-Mar-18 | 20-Jun-18 |
M2 | 10/01/2018 | 11-Apr-18 | 11-Jul-18 |
M3 | 07/02/2018 | 09-May-18 | 01-Aug-18 |
M4 | 02/03/2018 | 23-May-18 | 22-Aug-18 |
M5 | 09/03/2018 | 30-May-18 | 29-Aug-18 |
For more details about the project phases, milestones, etc. see More Schedule Details