Program Management
Mark Linkmeyer edited this page Jun 14, 2017
·
146 revisions
The following graphic shows the timeline of milestones associated with each release:
This graphic shows how the milestones of one release overlap those with the next release:
Milestone | Also Called | Definition |
---|---|---|
P0 | Planning Kickoff |
|
P1 |
|
|
M0 | Merge Window Open |
|
M1 | M1 Checkpoint |
|
M2 | M2 Checkpoint |
|
M3 | Feature Merge Window Close |
|
M4 | Code Freeze |
|
M5 | Release |
|
1.9 Schedule
Milestone | Planned | Trend | Actual | Notes |
---|---|---|---|---|
P0 | 22-Mar-17 (w12.3) | 31-Mar-17 (w13.5) | ||
P1 | 12-Apr-17 (w15.3) | 01-Jun-17 (22.4) | ||
M0 | 31-May-17 (w22.3) | 15-Jun-17 (w24.4) | Trending late due to delayed release of 1.8 | |
M1 | 21-Jun-17 (w25.3) | 21-Jun-17 (w25.3) | ||
M2 | 12-Jul-17 (w28.3) | 12-Jul-17 (w28.3) | ||
M3 | 02-Aug-17 (w31.3) | 02-Aug-17 (w31.3) | ||
M4 | 23-Aug-17 (w34.3) | 23-Aug-17 (w34.3) | ||
M5 | 30-Aug-17 (w35.3) | 20-Aug-17 (w35.3) |
__ Notation: wXX.Y where X is the week number (that starts on Mondays) and Y is the day of the week (1=Mon, 2=Tue, ... 6=Sat, 7=Sun)
Content coming...
Content coming...
© 2018-2023 Zephyr® Project. Zephyr is a trademark of the Linux Foundation.
Zephyr Project Home | Documentation Home | Mailing lists
Zephyr Project Home | Documentation Home | Mailing lists