-
Notifications
You must be signed in to change notification settings - Fork 7.5k
Program Management
Anas Nashif edited this page Feb 14, 2018
·
146 revisions
To see larger versions of the images below, right-click on them and open them in a separate browser tab or window.
The following graphic shows the timeline of phases and milestones associated with each release:
This shows how the phases and milestones of one release overlap with those of the next release:
Milestone | Also Called | Definition |
---|---|---|
P0 | Planning Kickoff |
|
P1 |
|
|
M0 | Merge Window Open |
|
M1 | M1 Checkpoint |
|
M2 | M2 Checkpoint |
|
M3 | Feature Merge Window Close |
|
M4 | Code Freeze |
|
M5 | Release |
|
Notation: wXX.Y - where X is the week number of the year (with weeks starting on Mon) and Y is the day of the week (1=Mon, 2=Tue, ... 6=Sat, 7=Sun)
Version | P0 | P1 | M0 | M1 | M2 | M3 | M4 | M5 |
---|---|---|---|---|---|---|---|---|
1.11 | 20-Sep-17 (w38.3) | 11-Oct-17 (w41.3) | 29-Nov-17 (w48.3) | 27-Dec-17 (w51.3) | 10-Jan-18 (w02.3) | 07-Feb-18 (w06.3) | 21-Feb-18 (w08.3) | 28-Feb-18 (w09.3) |
1.12 | 27-Dec-17 (w51.3) | 10-Jan-18 (w02.3) | 28-Feb-18 (w09.3) | 21-Mar-18 (w12.3) | 11-Apr-18 (w15.3) | 09-May-18 (w18.3) | 23-May-18 (w21.3) | 30-May-18 (w22.3) |
1.13 | 21-Mar-18 (w12.3) | 11-Apr-18 (w15.3) | 30-May-18 (w22.3) | 20-Jun-18 (w25.3) | 11-Jul-18 (w28.3) | 01-Aug-18 (w31.3) | 22-Aug-18 (w34.3) | 29-Aug-18 (w35.3) |
1.14 | 20-Jun-18 (w25.3) | 11-Jul-18 (w28.3) | 29-Aug-18 (w35.3) | 19-Sep-18 (w38.3) | 10-Oct-18 (w41.3) | 31-Oct-18 (w44.3) | 21-Nov-18 (w47.3) | 28-Nov-18 (w48.3) |
For more details about the project phases, milestones, etc. see More Schedule Details
© 2018-2023 Zephyr® Project. Zephyr is a trademark of the Linux Foundation.
Zephyr Project Home | Documentation Home | Mailing lists
Zephyr Project Home | Documentation Home | Mailing lists