Skip to content

Program Management

Alberto Escolar edited this page Sep 7, 2019 · 146 revisions

To see larger versions of the images below, right-click on them and open them in a separate browser tab or window.

Schedule

Schedule Milestones

The following graphic shows the timeline of phases and milestones associated with each release:

Schedule Milestones Graphic

This shows how the phases and milestones of one release overlap with those of the next release:

Overlapping Release Schedules Graphic

Milestone Definitions

Milestone Also Called Definition
P0 Planning Kickoff
  • Start Entering Requirements
P1
  • TSC Agrees on Major Features and Schedule
M0 Merge Window Open
  • All features, Sized, and Assigned
  • Merge Window Is Opened
M1 M1 Checkpoint
  • Major Features Ready for Code Reviews
  • Test Plans Reviewed and Approved
M2 Feature Merge Window Close
  • Feature Freeze
  • Feature Development Complete (including Code Reviews and Unit Tests Passing)
  • P1 Stories Implemented
  • Feature Merge Window Is Closed
  • Test Development Complete
  • Technical Documentation Created/Updated and Ready for Review
  • CCB Control Starts
M3 Code Freeze
  • Code Freeze
  • RC3 Tagged and Built
M4 Release
  • TSC Reviews the Release Criteria Report and Approves Release
  • Final RC Tagged
  • Make the Release

Actual and planned milestone dates

Version 2.1 (current) 2.2 2.3
P0 2019/06/28 2019/09/20 2019/12/27
P1 2019/07/19 2019/10/21 2020/02/07
M0 2019/09/06 2019/11/29 2020/02/28
M1 2019/10/11 2020/01/10 2020/04/10
M2 2019/11/08 2020/02/07 2020/05/08
M3 2019/11/22 2020/02/21 2020/05/22
M4 2019/11/29 2020/02/28 2020/05/29

In italic, actual schedule.

The 2.2 and 2.3 schedules are speculative

Past releases' schedules

Version 1.11 1.12 1.13 1.14 2.0
P0 20/09/2017 27-Dec-17 21-Mar-18 2018/06/27 2019/02/08
P1 11/10/2017 10-Jan-18 11-Apr-18 2018/07/18 2019/03/01
M0 29/11/2017 28-Feb-18 30-May-18 2018/09/05 2019/04/16
M1 27/12/2017 21-Mar-18 20-Jun-18 2018/09/26 2019/05/31
M2 10/01/2018 11-Apr-18 11-Jul-18 2019/02/08 2019/08/11
M3 02/03/2018 23-May-18 29-Aug-18 2019/03/15 2019/09/03
M4 09/03/2018 30-May-18 05-Sep-18 2019/04/16 2019/09/06

2.0 Release and freeze dates were delayed by 6 weeks to account for the summer holidays

Schedule Details

For more details about the project phases, milestones, etc. see More Schedule Details

Clone this wiki locally